Update:
May 7-11, 2007
The opening of the 1st Floor Women’s Restroom has been delayed until Tuesday or Wednesday for further tile, lighting & clean-up work. The closing of the Men’s Restroom is also delayed until the week of May 14th. Carpet in the staff area will be installed. Painting will continue as well as general clean-up of area. The new circulation counter will arrive in sections to be constructed later in the month. X-rays will be taken of the lower level floor where new plumbing equipment will be installed to make sure there are no other electrical ducts below. A city fire marshal and building inspector have been on site and have passed all the work done so far. Re-carpeting of the 3rd floor is scheduled for after hours the week of May 14th. Some areas of the floor will be closed off during the day in preparation of the night work.
|