Update:
March 19-23, 2007
The electrical work in the Borrower Services area that has been done so far has passed city inspection. The electrical work now moves to the Lower Level. The floors will be prepared for the installation of linoleum and carpet in April. New light fixtures will be installed along existing walls. Starting next Friday, March 23, the women’s restroom on the 1st Floor will be closed for 4 weeks to receive a thorough renovation. This includes
upgraded ventilation, new lighting, new stalls, sink area more open, baby changing station added and new paint. There are additional restrooms on the Lower Level and the 3rd floor.
|