Update:

March 12-16, 2007
Sprinkler head installation is finished and has passed inspections. Sheetrock repairs begin on columns and walls in Borrower Services area. Schedule is being finalized for all of the HVAC work and the workstation installation. Work on the ceiling of the 1st Floor women’s bathroom will begin Friday morning and may extend in to open hours. Signs will be posted if restroom is not available. Electrical and data connection work also continues.