Update:
June 4-8, 2007
Work continues in the 1st Floor Men’s restroom with closing up walls, tile replacement and painting. The 1st floor staff workstations are being completed as well as the walls around the new sorting area. Fire and card key systems will be upgraded in that area. Plaster repairs are continuing as well as lower level plumbing equipment installation.
New cabinets for staff and public areas have been delivered and will be put into place after the limestone, granite and carpet in the circulation area is laid. The glass enclosure around the self-return stations will also be started this week.
|