Update:
February 20-23, 2007
Work continues on the sprinkler heads, floor outlets and air conduits in the Borrower Services staff area. Subcontractors continue to submit samples of flooring, cabinetry, limestone, glass, toilet accessories, ceiling tiles and metal accessories to be used later in the project. Modifications to the air ducts and exhaust fans for the upgrade to the restrooms have delayed the start of the renovation there.
The closing of the 1st floor women’s restroom will not be for at least another week.
|