Update:
April 30-May 4, 2007
In the 1st Floor staff area the remaining linoleum will be installed this week with the carpet installation the following week. The replacement of the 3rd floor carpet is scheduled for the week of May 14-18. The limestone for the stair and desk area is arriving this week for installation next week. The final tiling and the installation of the new partitions in the 1st Floor women’s restroom will be completed this week with painting and clean-up to follow. The library hopes to open the restroom on the Friday.
The 1st Floor Men’s Restroom will then close on Tuesday, May 8th. The Lower Level electrical and ductwork will be finished this week and new plumbing equipment will be installed.
|