Update:
April 23-27, 2007
Most of the work in the 1st Floor Women’s Restroom will be completed this week.
The restroom is scheduled to be re-opened on Friday, April 27. The first
week of May the restroom will be closed for 2 days again to finish the
ceiling access panels and painting.
During the 1st week of May the 1st Floor Men’s Restroom will be closed for
renovation for 4 weeks. Men’s restrooms are available on the Lower Level
and the 3rd Floor.
Linoleum will continue to be installed in the staff area of the
1st floor and the new carpet will be delivered. Plaster work
in the area will begin. Plumbing and HVAC work will continue i
n the Lower Level. Re-carpeting of the central portion of the
3rd floor will begin the second or third week of May during
closed hours. Portions of the floor may be closed off for a day at a time.
|